I-10 White Oak Bayou: Houston’s $400 Million Fix for the Flood-Prone Stretch

I-10 White Oak Bayou: Houston’s $400 Million Fix for the Flood-Prone Stretch

A 1.8-mile stretch of I-10 in Houston floods in heavy rain. TxDOT is raising the main lanes above the White Oak Bayou floodplain. The project runs from Heights Boulevard to I-45 and costs $407 million. Work runs from 2024 to 2028, with the worst closures lasting into 2028. The I-10 eastbound connector to I-45 north stays closed into 2028. This guide explains the fix, the timeline, and how to drive around it.

Why this stretch floods

White Oak Bayou runs beside I-10 through the Heights and downtown. The old main lanes sat low, inside the bayou’s 100-year floodplain. Heavy rain could close the freeway when drivers needed it most. Raising the lanes removes the flood risk for the mainlanes. Our Houston subsidence guide explains why parts of the city keep sinking and flooding. The fix also rebuilds the HOV lanes and the Houston Avenue Bridge.

What the project builds

Crews are lifting the existing main lanes out of the floodplain. The work covers 1.8 miles, from Heights Boulevard to I-45. A detention pond and a shared-use path go in on the north side. The Houston Avenue Bridge will be demolished and rebuilt, starting in 2027. The project is financed by state funds, including $90.5 million from Texas Clear Lanes. Webber LLC is the main contractor, and work began on January 6, 2025.

The closures drivers face

Westbound I-10 runs on two lanes between I-45 and Houston Avenue. The I-10 eastbound connector to I-45 north stays closed into mid-2028. The I-45 southbound connector to I-10 westbound was closed too. The HOV lanes closed on October 9, 2026, for demolition and rebuilding. Eastbound HOV reopens in fall 2027, and westbound HOV in summer 2028. Check Houston TranStar before every trip through the work zone.

How to drive around it

Use Studemont Street or the Shepherd and Durham corridor instead. Allen Parkway works as a bypass for some downtown trips. Allow extra time, since the work zone slows traffic in both directions. Nightly ramp and street work can close lanes with little warning. Families in the Heights can check our best neighborhoods in Houston guide. The payoff is a freeway that stays open in the next big storm.

Frequently Asked Questions

How much does the I-10 White Oak Bayou project cost?

$407 million, financed by state funds, including $90.5 million from the Texas Clear Lanes initiative.

How long is the work zone?

1.8 miles, from Heights Boulevard to I-45, including the HOV lanes and the Houston Avenue Bridge.

When will the project finish?

TxDOT lists the timeline as 2024 to 2028, with the I-10 eastbound connector to I-45 north closed into mid-2028.

Why raise the freeway instead of widening it?

The old lanes sat in the bayou’s 100-year floodplain. Raising them removes the flood risk for the mainlanes.

What is closed right now?

Westbound I-10 runs on two lanes near downtown, and the HOV lanes are closed for rebuilding. Check Houston TranStar before you drive.

Will the Houston Avenue Bridge close?

Yes, it will be demolished and rebuilt, with construction starting in 2027.